10.
▪At the beginning of a project, a software team project manager is given a schedule with everyone’s vacations on it. She realizes that because the software will be delivered to the QA team exactly when they have overlapping vacations, there is a serious risk of quality problems because there won’t be anyone to test the software before it goes into production. What BEST describes the constraint this places on the project?